Project Summary
Major Civil Engineering works including:
- Traffic Management
- Site Clearance,
- Design and construction of a temporary carriageway through unsuitable ground conditions
- Design and Construction of 1200m2 buried bridge involving
- 184 no. 14m long Precast Concrete Piles including Pile testing
- Stripping of Piles and construction of Pile Caps
- Installation of 3no. 600mm Piped Culverts
- Construction of Bridge Deck involving Placing of Mud Mat (90m3 of Concrete) 8no connected slabs (82t of Reinforcing, 600m3 of 40N Concrete), Laying of Various jointing materials, Finishing of Slab, Waterproofing and laying of Sand Carpet,
- 1650m2 of Carriageway Surfacing including AC20 Binder Course and HRA Surface Course
- Accommodation works including fencing (700m), verge construction
- Road Markings
- Completion of the Structural and Geotechnical Approval process for the new structure
- Installation of a Type 6 EMR Buried Joint
Project Gallery
Specifications
- Project Name: B127 Newbridge Road Lisnaskea Flood Alleviation Works
- Client: DFI Roads Service
- Supervisor: Byrne Looby
- Date: Dec 2017 – June 2018
- Value: £800,000