Killybearn Road

Project Summary

Major Carriageway resurfacing works including:

  • Traffic Management
  • Site Clearance
  • 1000m2 of Carriageway Milling at 100mm depth plus disposal of waste
  • 3000m2 of Maccaferri Mesh installation for carriageway strengthening
  • 3500m2 of Carriageway Surfacing including AC14mm Binder Course and AC20mm Special Wearing Course
  • Accommodation works including: AC10mm Entrance Surfacing, Side filling, Construction of drainage outlets
  • Road Markings including: White Lining, Reflective Road Studs

Project Gallery

Specifications

  • Project Name: Killybearn Road
  • Client: DFI Roads Service
  • Supervisor: DFI Consultancy
  • Date: June 2019
  • Value: £140k

Get in touch